February 22, 2021 9:36 AM
The street lights will be installed in the 204th St roundabout area starting today (2-22) through next Tuesday. No work will be performed on Thursday. Traffic control will be in place, please expect short delays when traveling in this area.
February 19, 2021 4:18 PM
Starting on Monday, Feb. 22, and throughout the week, there will be single lane closures on 71st Avenue (off of 204th Street) for Pilchuck Village’s sewer connection.
February 5, 2021 1:50 PM
If you are experiencing brown water, the Water Department has been made aware and is investigating the cause
January 20, 2021 10:13 AM
The temporary stop light at Island Crossing (SR530 and Smokey Point Blvd.) will be replaced with a pole signal.
Work begins this week on the shoulder. This should not affect traffic flow, but use caution in this area. Night work will start next week from 9pm to 5am.
Read On...
January 15, 2021 10:14 AM
The contractor will be working to finish up the concrete work and pave the entrance at Banner Bank on Monday. Current traffic control plan will be in place. Expect some delays.
January 6, 2021 3:05 PM
Concrete pouring Thursday...
On Thursday, January 7, crews will be pouring the concrete on the south side of 204th Street for curb and sidewalks. Large trucks, please continue to use the truck detour routes until further notice. ...
Read On...
December 30, 2020 11:40 AM
Flaggers onsite to direct truck traffic.
The flaggers that are onsite at 204th roundabout project, directing large trucks to detour route will extend until midnight on 12-30-20 . They will be pouring the splitter islands today on 77th and the east side of 204th as well as re-pouring the center...
Read On...
December 8, 2020 10:16 AM
The signal at the intersection of Smokey Point Blvd and 173rd Street is going to be out on Wednesday, Dec. 9. There will be a police officer directing traffic at the intersection while the signal is out. It will likely only be out for a few hours, but...
Read On...
December 1, 2020 2:47 PM
Contractor hit a water line on Park Hill Drive and are currently working to repair it.