Project Description
The City of Arlington will be replacing and up sizing the 67th Ave Trunk Sewer Main. This replacement work will occur between Woodlands Way to approximately 200th Pl. The current 12-inch pipe will be replaced with a 15-24-inch pipe to increase the flow and intake capacity.
Project Benefits
- Increase capacity
- Replace aging infrastructure
- Expand sewer capacity
- Support new development
Project Cost and Funding
- Estimated cost: $1,800,000
- Funding by: City of Arlington Utility Funds
Project Schedule
- Design: 2023
- Estimated Construction start: 2024
Coordination with Local Businesses / Residents
Regular schedule updates will be provided by the City to keep local businesses and community apprised of the project progress and any potential impacts.